  "archetype": {
    "code": "a3",
    "n": 3
  },
  "current_thesis": "Alliant Energy is more likely to lag than lead the S&P 500 over three months: data-center contracts lift its outlook, but a utility guiding about 8% earnings growth offers little room to outrun the index; the fourth-quarter report expected around 19 February 2027 tests it. On 29 October 2026 the company reported third-quarter GAAP EPS of $1.52 against $1.09, set 2027 ongoing EPS guidance at $3.63–3.73 and raised its 2027–2030 capital plan 19% to $15.9 billion on 3.4 GW of contracted data-center demand.",
  "invalidation_trigger": "2026 ongoing EPS at the fourth-quarter 2026 report above $3.46, known by February 2027; or new data-center contracted demand signed beyond the 3.4 GW, announced by the fourth-quarter 2026 report at least 1 GW, known by February 2027.",
  "kill_line_kind": "business_test",
  "kill_line_due": "2027-02-28",
  "catalyst_date": "2027-02-19",
  "catalyst_estimated": true,
  "portfolio": null,
  "pick": null,
  "themes": [
    "industrial-power-grid",
    "ai-datacenter-infrastructure"
  ],
  "tags": [],
  "sources": [],
  "caveats": [
    {
      "claim": "Alliant's ongoing EPS and its guidance are non-GAAP measures that exclude certain items; third-quarter 2026 GAAP and ongoing EPS were both $1.52, but nine-month figures differ ($3.04 GAAP, $2.99 ongoing).",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    }
  ],
  "source_links": [
    {
      "title": "ALLIANT ENERGY CORP - Form 8-K - FY2026",
      "url": "https://www.sec.gov/Archives/edgar/data/0000352541/000035254126000045/lnt102920268-kex991.htm",
      "date": "2026-10-29"
    },
    {
      "title": "energy.gov",
      "url": "https://www.energy.gov/articles/energy-department-closes-51-billion-loan-lower-electricity-costs-and-strengthen-grid",
      "date": null
    },
    {
      "title": "Order also opens investigation into IPL’s management efficiency",
      "url": "https://iuc.iowa.gov/press-release/2026-08-26/iuc-reduces-ipl-gas-rates",
      "date": "2026-08-26"
    },
    {
      "title": "DOE Closes $5.1 Billion Loan to Help Alliant Energy Lower Bills in Iowa, Wisconsin",
      "url": "https://www.tdworld.com/policy/article/55415095/doe-closes-51-billion-loan-to-help-alliant-energy-lower-bills-in-iowa-wisconsin",
      "date": null
    },
    {
      "title": "psc.wi.gov",
      "url": "https://psc.wi.gov/Documents/PressReleases/05.08.26PressRelease.PDF",
      "date": null
    }
  ],
  "evidence": [
    {
      "claim": "Third-quarter 2026 GAAP EPS was $1.52, against $1.09 a year earlier; ongoing EPS was $1.52, against $1.12.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "2026 ongoing EPS guidance was narrowed to $3.41–3.46 from $3.36–3.46, and 2027 ongoing EPS guidance was set at $3.63–3.73.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "The 2027–2030 capital plan is about $15.9 billion, up 19% from the prior forecast: $4,305 million in 2027, $4,735 million in 2028, $4,285 million in 2029 and $2,610 million in 2030.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "Contracted data-center demand totals 3.4 GW across IPL and WPL, and the company expects peak demand to rise about 60% by 2031.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "Third-quarter operating revenue was $1,285 million against $1,210 million a year earlier, and net income was $398 million against $281 million.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "The Department of Energy closed a $5.1 billion, 30-year loan package: up to $3.5 billion for IPL and up to $1.626 billion for WPL, for gas generation, storage and plant upgrades.",
      "source": "Department of Energy press release",
      "as_of": "2026-10-28"
    },
    {
      "claim": "The 2027 dividend target is $2.25 a share, up from $2.14, with growth moderated to help fund the capital plan.",
      "source": "Third-quarter 2026 earnings release, Form 8-K exhibit 99.1",
      "as_of": "2026-10-29"
    },
    {
      "claim": "The Iowa Utilities Commission reduced IPL's gas rates and opened an investigation into IPL's management efficiency.",
      "source": "Iowa Utilities Commission press release",
      "as_of": "2026-08-26"
    }
  ],
  "view_changes": [],
  "frame": {
    "as_of": "2026-11-25",
    "business": "Alliant Energy owns two regulated Midwest utilities, Interstate Power and Light (Iowa) and Wisconsin Power and Light, selling electricity and natural gas to homes, businesses and industry and earning a regulator-approved return on rate base. Third-quarter 2026 operating revenue was $1,285 million.",
    "change": {
      "now": "On 2026-10-29 the company raised its 2027–2030 capital plan 19% to $15.9 billion on 3.4 GW of contracted data-center demand and set 2027 ongoing EPS guidance at $3.63–3.73.",
      "next": "Spending of $4,305 million in 2027 and $4,735 million in 2028 is funded partly by a $5.1 billion Department of Energy loan closed 2026-10-28, while dividend growth is slowed to a $2.25 target.",
      "linked": "Meta Platforms (META) is expected to begin transmission service in Wisconsin in the first quarter of 2027, per the 2026-10-30 call; data-center customers pay for the new gas, battery and transmission build."
    },
    "priced_in": "Filed valuation multiples are not available, because the filed figures run only to 2026-03-31, before the 2026-10-29 third-quarter results (nine-month revenue $3,440 million, net income $792 million). The 2026-11-24 close of $72.58 assumes delivery of 2027 ongoing EPS of $3.63–3.73 while funding a $15.9 billion plan.",
    "priced_in_filed": null,
    "links": {
      "customers": [
        {
          "ticker": "META",
          "url": "https://frontierpicks.com/dossiers/META/"
        }
      ],
      "suppliers": [],
      "competitors": []
    }
  },
  "filed_numbers": {
    "as_of": "2026-11-25",
    "sector": "Utilities",
    "financials": {
      "status": "not available",
      "reason": "the newest filed quarter ends 2026-03-31",
      "close_date": "2026-11-25",
      "latest_quarter": null,
      "figures": {}
    },
    "short_interest": {
      "status": "ok",
      "settlement": "2026-10-30",
      "published": "2026-11-10",
      "short_pct_of_outstanding": null,
      "days_to_cover": 9.3,
      "change_pct": 4.1
    },
    "insiders": {
      "status": "not available yet",
      "as_of": null,
      "windows": []
    }
  },
  "body_markdown": "## Current Thesis\n\nAlliant Energy is more likely to lag than lead the S&P 500 over the next three months. Its data-center contracts have raised its growth outlook, but a regulated utility guiding to about 8% earnings growth gives the shares little room to outrun the index over a quarter. The fourth-quarter 2026 report, expected around 2027-02-19, shows whether 2026 earnings land above the top of guidance or new data-center contracts arrive early.\n\nThe case is real. On 2026-10-29 the company reported third-quarter GAAP earnings per share (EPS) of $1.52, up from $1.09 a year earlier. It narrowed 2026 ongoing EPS guidance to $3.41–3.46 and set 2027 ongoing EPS guidance at $3.63–3.73. It also raised its 2027–2030 capital plan 19% to $15.9 billion on 3.4 gigawatts (GW) of contracted data-center demand. Those facts lift the earnings path. A plan of that size also needs a great deal of new debt and equity, and the company slowed dividend growth to help fund it.\n\nThe rating is Low because the case rests on steady, regulator-set growth. Reported results show that growth, and they give no sign of a surprise large enough to beat the index within a quarter. Five brokers raised price targets after the report, and the shares have risen 6.1% over three months, so the good news is already widely known.\n\n## Bull Case\n\n- **Data-center demand reshapes the load forecast.** Five signed data-center agreements total 3.4 GW of contracted demand, and the company expects peak demand to rise about 60% by 2031 (third-quarter release, 2026-10-29). Meta Platforms is expected to begin taking transmission service in Wisconsin in the first quarter of 2027 (earnings call, 2026-10-30).\n- **Earnings growth accelerated in 2026.** Ongoing EPS for the first nine months of 2026 was $2.99, up 14% from $2.62, and third-quarter net income was $398 million against $281 million a year earlier (third-quarter release, 2026-10-29).\n- **Cheaper federal debt funds the build.** On 2026-10-28 the company closed a $5.1 billion, 30-year loan package from the Department of Energy's Office of Energy Dominance Financing. Interstate Power and Light (IPL) can borrow up to $3.5 billion and Wisconsin Power and Light (WPL) up to $1.626 billion. The company estimates up to $1.2 billion of customer savings over the loans' life (Department of Energy release, 2026-10-28).\n- **More contracts targeted soon.** On 2026-10-31 the company set a goal of securing 1 GW of new data-center contracts within six months, on top of the 3.4 GW already signed (company news, 2026-10-31).\n- **Brokers lifted targets after the report.** Jefferies raised its target to $82 (2026-11-03), Wells Fargo to $82 with an Overweight rating (2026-11-02), BMO Capital to $79 (2026-11-02), HSBC to $78 (2026-11-16) and Ladenburg Thalmann to $77 (2026-11-20).\n\n## Bear Case\n\n- **Financing needs weigh on per-share growth.** At 2026-09-30 the company carried $11,085 million of long-term debt, $374 million of current maturities, $704 million of commercial paper and $400 million of other short-term borrowings against $26 million of cash (third-quarter release, 2026-10-29). A plan of $4,305 million in 2027 and $4,735 million in 2028 adds to that.\n- **Dividend growth slowed to fund spending.** The 2027 dividend target is $2.25 a share, up from $2.14, with growth deliberately moderated to help pay for the larger capital plan (third-quarter release, 2026-10-29).\n- **Iowa regulators are scrutinising costs.** On 2026-08-26 the Iowa Utilities Commission reduced IPL's natural gas rates. It found executive charter-flight spending inconsistent with the rate settlement and opened an investigation into IPL's management efficiency (Iowa Utilities Commission release, 2026-08-26).\n- **Iowa base rates are frozen through 2030.** IPL extended its Iowa retail electric base rate stability plan by one year, through 2030 (third-quarter release, 2026-10-29). That limits how quickly new Iowa spending reaches customer rates outside other recovery paths.\n- **Costs rose alongside revenue.** Third-quarter operations and maintenance, depreciation and financing expenses all increased, partly offsetting higher rate-base revenue (third-quarter release, 2026-10-29).\n\n## Setup & Price Structure\n\nThe shares closed at $72.58 on 2026-11-24, above the 50-day moving average of $68.3 and the 200-day moving average of $70.11. They are up 6.1% over three months. The 52-week closing low was $63.21 on 2026-09-28, a month before the third-quarter report. The 52-week intraday high was $78.81 on 2026-07-07, and the last close sits 7.9% below it.\n\nAcross the five sessions to 2026-11-24, closes held between $71.31 (2026-11-17) and $72.58. The most recent broker targets, $77–82, sit above the July high. The fourth-quarter report and any new contract announcements are the next business events that bear on the price. Tests across US stocks have found no reliable effect so far from where a stock sits against its recent highs or lows.\n\n## Catalyst Calendar\n\n- **~2027-02-19 (est.):** Fourth-quarter and full-year 2026 results. Shows whether 2026 ongoing EPS beats the $3.46 top of guidance, updates the 2027 guide and financing plan, and reports progress toward 1 GW of new data-center contracts.\n- **~2027-05 (est.):** First-quarter 2027 results. The first quarter in which Meta's Wisconsin transmission service is expected to begin; it shows whether data-center load starts reaching sales and earnings.\n\n## What Would Change Our Mind\n\n2026 ongoing EPS at the fourth-quarter 2026 report above $3.46, known by February 2027; or new data-center contracted demand signed beyond the 3.4 GW, announced by the fourth-quarter 2026 report at least 1 GW, known by February 2027.\n\n## Correlation Notes\n\nAlliant trades as a regulated Midwest electric and gas utility with a data-center growth overlay. A common market view is that utility shares move against long-term Treasury yields, because investors compare dividends with bond income. On that view, the shares follow rates and the utility sector more than the broader index over a quarter.\n\nThe data-center link ties the shares loosely to AI infrastructure spending through Meta Platforms (META) in Wisconsin and the QTS campus in Cedar Rapids, Iowa. A slowdown in hyperscaler spending would reach Alliant through delayed energisation dates more than through current earnings. Across liquid US stocks, the spread of 63-session returns was 27% (standard deviation) in 2026. Against that spread, a utility's quarter is usually decided by the sector and by rates.",
  "first_seen": "2026-11-24",
  "last_analyzed": "2026-11-25T19:21:20+00:00",
  "last_synthesized": "2026-11-25",
  "date_modified": "2026-11-25",
  "license": "Content © FrontierPicks. Cite the canonical URL."
}