FRMI · Fermi
Conviction · Low · more likely to lag the S&P 500 over the next three months
Wrong if: a daily close above $3.68
Updated ·
Price against the kill line
29.1% clear of its kill line on the 13 November 2026 close.
How to read this
This note expects the shares to lag the market, so its kill line sits above the price: a close above the red mark would prove the view wrong. Prices run from low on the left to high on the right. The dot is where the stock closed on 13 November 2026, left of the mark while it is below the line; a dot right of the mark has closed through it.
The scale is stretched near the line, so close calls are easy to see. More than 8% from the line, the stock reads well clear, with a hollow dot to show the figure is off the drawn scale.
The kill line is the research note's own test. The portfolio sells on business facts, not on a price. How the portfolio decides
Three months against the kill line
Daily closes, to . Red: the kill line, a daily close above $3.68, set on 12 November 2026. The shares are down 57.5% since the close; the S&P 500 is down 2.1% over the same sessions. Figures in the note can cover a different window.
Kill line
A daily close above $3.68, the 50-day moving average as of 11 November 2026, which would show the shares leading; or a signed definitive long-term lease for the full 600 megawatts together with project financing for the build.
Research onlyNot in the portfolio.
Key figures from the filings · Real Estate
Quarter to 30 September 2026, filed 12 November 2026
- Net cash, cash less debt ($M)
- −672
All filed numbers
What Fermi reports to the SEC in its quarterly and annual filings. Each group states its period and filing date once; a figure dated otherwise says so. Built from the filings known on .
| Pre-tax income ($M) | Not reported |
| Net income ($M) four quarters: −489 | −142 |
| Diluted shares, change on a year (%) against the quarter to 30 September 2025 | +37.8 |
| Operating cash flow ($M) | −136 |
| Capital spending ($M) | Not available |
| Free cash flow ($M) | Not available |
| Cash and short-term investments ($M) | 286 |
| Debt ($M) long-term debt | 958 |
| Net cash, cash less debt ($M) | −672 |
| Deferred revenue ($M) | Not reported |
| Backlog, orders not yet delivered ($M) | Not reported |
| Receivables ($M) | Not reported |
| Inventory ($M) | Not reported |
| Shareholders' equity ($M) | 959 |
| Market value ($M) | 1,689 |
| Enterprise value, market value plus net debt ($M) | 2,361 |
| Enterprise value to sales (×) | Not available |
| Enterprise value to operating income (×) | Not meaningful |
| Price to earnings (×) | Not meaningful |
| Price to book value (×) | 1.8 |
| Free-cash-flow yield (%) | Not available |
Short interest (FINRA, settled 15 October 2026, published 13 November 2026): 9.8% of shares outstanding sold short, 2.7 days of average trading to cover, −5.1% since the previous report.
| Window | Bought | Sold |
|---|---|---|
| 90 daysfrom | $0 | $28.7M |
| 12 monthsfrom | $0 | $103.8M |
The thesis
Fermi Inc. shares are more likely to lag the S&P 500 over the next three months. A $200 million prepayment from an unnamed investment-grade hyperscaler gives the Project Matador campus in Texas a real customer. The definitive long-term lease is still unsigned, though. Fermi's own 10-Q, filed 12 November 2026, says its resources fall short of its obligations due within one year. The next test is whether the customer starts work on site by the 1 December 2026 target. A signed lease for the full 600 megawatts (MW), with financing for the build, would break this call.
The rating is low because the good news replaces a failed deal and adds no revenue yet. On 12 November 2026 Fermi reported a third-quarter net loss of $141.6 million, or $0.22 per share, with no revenue. In the same release it said the TensorWave data-center lease signed in August 2026 had been terminated, along with the related AMD credit-support agreement. Management said the $200 million wire was due by 13 November 2026. Fermi had not publicly confirmed receipt as of that date.
The price reflects a high chance that Matador stays without contracted revenue. The shares closed at $2.06 on 12 November 2026, 90.8% below the 52-week intraday high of $22.37 set on 12 November 2025.
Bullish and bearish views on Fermi Inc.
The bull case on Fermi Inc. (FRMI), in brief: investment-grade customer replaces a neocloud. The bear case: the 10-Q flags going-concern doubt.
Bull case
- Investment-grade customer replaces a neocloud. Fermi's 12 November 2026 release describes a $200 million prepayment and a $15 million early construction agreement for an initial 600 MW starting in 2027. On the 12 November 2026 call, the chairman said a further $90 million steel and building-materials agreement is being negotiated.
- Management gave dated near-term milestones. On the 12 November 2026 earnings call, management said the customer plans to begin mobilizing on site by 1 December 2026. It targeted first power for the first building in late second quarter or early third quarter of 2027.
- A near-term lender deadline is gone. On the same call, management said an amendment to its MUFG turbine financing removed a 10 November 2026 lease deadline and kept minimum principal payments at 5%. Management put the cost at about $25 million in fees and said the change avoids more than $55 million of payments over three quarters.
- The physical asset is large. The 12 November 2026 release puts net property, plant and equipment at about $1.67 billion. The CEO cited 2.2 gigawatts of current capacity, and the release refers to permitted levels of about 6 gigawatts.
Bear case
- The 10-Q flags going-concern doubt. Fermi's 10-Q for the quarter ended 30 September 2026 says its resources "are not sufficient to satisfy the Company's financial obligations as they become due within one year." Management concludes that its plans, including undrawn equipment financing and timing capital spending to tenant deals, alleviate that doubt.
- Debt is large against cash. At 30 September 2026 Fermi held $286.3 million of unrestricted cash and $29.2 million of restricted cash, per the 10-Q. Debt principal was $999.9 million, or $958.4 million net of issuance costs. The $444.9 million turbine warehouse facility matures on 10 August 2027.
- Lenders already granted a waiver. The 10-Q says turbine-facility lenders waived potential defaults on a one-time basis on 9 October 2026, tied to relocation of financed equipment and insurance requirements. The Yorkville promissory note expired undrawn on 1 October 2026.
- The lease is still not signed. On the 12 November 2026 call, management gave no signing date and called talks "very, very far along." TensorWave's lease missed its 31 October 2026 closing deadline before it was terminated.
- The founder is selling hard. SEC Form 4 filings show 10% owner Toby Neugebauer sold 4,047,200 shares at an average $3.55 on 13 October to 14 October 2026 and 420,749 at $3.04 on 20 October 2026. He sold another 7,657,800 shares at an average $1.70 between 3 November 2026 and 5 November 2026.
- The governance fight is open. Fermi's 4 November 2026 8-K says neither Class I nominee, Rick Perry or Jeffrey Stein, won a majority of shares outstanding at the 30 October 2026 meeting. The company says Neugebauer-affiliated holders breached a nomination agreement, and those holders dispute this.
Price setup
The shares closed at $2.06 on 12 November 2026, up from $1.81 on 11 November 2026, in the session the hyperscaler agreements were announced. The 52-week closing low is $1.53, set on 5 November 2026, inside the window of the founder's 7,657,800-share sale. The 3-month change is −67.8%, from a $6.40 close on 14 August 2026.
As of 12 November 2026, the 50-day moving average was $3.63 and the 200-day moving average was $6.12. Both sit far above the last close. The founder's October sales at $3.04–$3.73 mark the range the shares held before the TensorWave lease failed. A return to that range would need a signed lease and a plan to fund the 600 MW build without heavy dilution. Management says it aims for "little or no dilution" and wants to fund the build with customer prepayments and project-level debt. The 10-Q counts 646,953,440 shares outstanding on 5 November 2026.
Catalysts ahead
- ~1 December 2026 (est.): Target for the hyperscaler to begin mobilizing on site at Project Matador. Physical work by the customer before a lease is signed would show the 600-megawatt deal moving toward a definitive lease.
- ~31 March 2027 (est.): Fourth-quarter and full-year 2026 results and 10-K. Shows whether a definitive lease is signed, how the build will be funded, and whether the going-concern doubt remains.
Elapsed catalysts
- ~13 November 2026 (est.): Deadline for the hyperscaler's $200 million prepayment wire, per management on the 12 November 2026 call. A confirmed receipt shows the customer is committed and adds cash against $999.9 million of debt principal. A missed wire would repeat the TensorWave failure. (passed)
What would change the view
A daily close above $3.68, the 50-day moving average as of 11 November 2026, which would show the shares leading; or a signed definitive long-term lease for the full 600 megawatts together with project financing for the build.
What it trades with
Fermi trades with AI data-center and power names on broad sector days. On 11 November 2026, when the Nasdaq 100 rose 2.8% as CoreWeave and Nvidia climbed, the shares went from a $1.54 close to $1.81. On 12 November 2026 the shares rose on company news while Nvidia fell 5% on its chief executive's exit, per market reports that day. Most of the 3-month move comes from company events: the TensorWave lease, the board vote, the founder's sales and the hyperscaler package. Those events will decide the next three months more than the sector will. A sector-wide pullback in AI spending, like the post-midterm selloff reported on 6 November 2026, would add pressure on a pre-revenue company carrying $999.9 million of debt principal.
Notes
- Fermi was pre-revenue as of its third-quarter 2026 report; its value rests on signing leases at the Project Matador campus in Texas.
- Fermi's 10-Q for the quarter ended 30 September 2026 discloses substantial doubt about going concern, which management concludes its plans alleviate.
- Two Class I board seats are in dispute: neither nominee won a majority of shares outstanding at the 30 October 2026 annual meeting, and both serve until a successor is elected.
- Co-founder and former CEO Toby Neugebauer is the largest shareholder, is in a public dispute with the board and has been selling shares in the open market.
The evidence, claim by claim (8)
- Third-quarter 2026 net loss of $141.6 million, or $0.22 per share, with no revenue; general and administrative expense of $142.2 million included $65.8 million of stock compensation. Fermi 8-K Exhibit 99.1, 12 November 2026 · as of
- The 10-Q says resources measured against forecast disbursements are not sufficient to meet obligations due within one year; management concludes its plans alleviate the substantial doubt. Fermi 10-Q for the quarter ended 30 September 2026, filed 12 November 2026 · as of
- Unrestricted cash of $286.3 million and restricted cash of $29.2 million against debt principal of $999.9 million ($958.4 million net of issuance costs). Fermi 10-Q for the quarter ended 30 September 2026, filed 12 November 2026 · as of
- The $444.9 million turbine warehouse equipment facility matures on 10 August 2027; its lenders waived potential defaults on a one-time basis on 9 October 2026. Fermi 10-Q for the quarter ended 30 September 2026, filed 12 November 2026 · as of
- Agreements with an undisclosed investment-grade hyperscaler: $200 million prepayment and $15 million early construction deal for an initial 600 megawatts from 2027; definitive lease not yet signed. Fermi 8-K Exhibit 99.1, 12 November 2026 · as of
- The TensorWave data-center lease signed in August 2026 and the related AMD credit-support agreement were terminated. Fermi 8-K Exhibit 99.1, 12 November 2026 · as of
- 10% owner Toby Neugebauer sold 7,657,800 shares at $1.52–$2.04 (average $1.70) from 3 November to 5 November 2026. SEC Form 4 filed 5 November 2026 · as of
- Neither board nominee (Rick Perry, Jeffrey Stein) won a majority of shares outstanding at the 30 October 2026 annual meeting; Fermi alleges Neugebauer-affiliated holders breached a nomination agreement. Fermi 8-K filed 4 November 2026 · as of
Sources
- SEC EDGAR
- Fermi Inc. - Form 8-K - FY2026 · sec.gov ·
- Fermi Inc. (FRMI) Q3 2026 Earnings Call Transcript · fool.com ·
- Fermi Inc. - Form 8-K - FY2026 · sec.gov
- Fermi says an unnamed hyperscaler will prepay $200 million for 600 MW at Project Matador · startupfortune.com
- Fermi Paid $25M to Drop a 400 MW Lease Deadline on Its Loan · fourweekmba.com
- Why Is Fermi Stock Gaining Thursday? · benzinga.com
Related · shared themes
CEG
Constellation Energy
Constellation Energy's third-quarter beat and raised $12.50–$12.80 guidance make its shares modestly more likely than not to beat the S&P…
FPS
Forgent Power Solutions
Forgent Power Solutions is modestly more likely than not to beat the S&P 500 over three months, after beating guidance and guiding fiscal…
PSIX
Power Solutions International
Power Solutions International's record third-quarter profit, raised second-half outlook and new multi-year engine supply deal support the…
BE
Bloom Energy
Bloom Energy shares look more likely to lag the S&P 500 over three months: the 11 November rebound followed CoreWeave's results, while…